Phase 1 Week 1 06/02/2015 – 06/06/2015
This project at 1652 Victor is underway with evaluation done. Permits are in the process of being pulled for the Electrical. In the videos below, Electrician explains in detail what needs to be done and the route to take.
Phase 2 Week 2 06/07/2015 – 06/13/2015
Installing Drywall to Ceilings after insulation
Ceilings and Drywall Installation
Replacing Wall in Bathroom with Tile
1652 Victor Painting and Mudding
Phase 3 Week 3 06/17/2015 – 06/21/2015
Painting and Finishing of Walls and Ceilings
Re-Evaluation On Victor
03/25/2019 Re-Evaluating Property
Re-Evaluation Of Property
Re-Evaluation 2
Re-Evaluation On Victor 2
12/04/2019
Re-Evaluation Of Property
Re-Evaluation 2
Recent Comments