Phase 1 Week 09/04/2015 – 09/10/2015
Phase One of 2020 Riverside Blvd. Rehab Project is about to began. Starting with demolition. This Project is going to take approximately 30 days to complete if the weather permits. This property is being prepared for maximum cash flow utilizing Shared Independent living.
Flowers and Associates Construction Team members will lead the way in repair and formatting rooms while Media Team keep you up to date on progress through video and pics.
Phase 2 Week 09/11/2015 – 09/16/2015
Installing Insulation
Floor Installation
Electric Evaluation
Electric Evaluation Continued
Phase 3 Final Week 11/01/2015 -11/25/2015
Internal Electric Evaluation and Plug change out
Moldings And Trim
Moldings and Trim 2
Carpet and Flooring Installation
Final Touches For Riverside
Wall Plate Installation
Furniture Setup
Pressure Washing Exterior Brick
Pressure Washing Front Area